Antalya Metropolitan Municipality


Main Company : Doğşen İnşaat A.Ş

Date of Start : 15.02.2004

Date of End : 30.05.2004

Length of the Tunnel : 4500m

Diameter of the Tunnel : Supply Canal

Giresun Dereli Çırakdamı HES


Main Company : Bereket Enerji A.Ş

Date of Start : 09.01.2007

Date of End : 10.06.2009

Length of the Tunnel : 4800m

Diameter of the Tunnel : 5.20m x5.20m

Mersin Erdemli Lamas III-IV HES


Main Company : Kanyon Enerji

Date of Start : 23.10.2007

Date of End : 28.01.2009

Length of the Tunnel : 1360m

Diameter of the Tunnel : 4.80m x3.80m

Giresun Şebinkarahisar HES Project


Main Company : Kanyon Enerji

Date of Start : 04.01.2009

Date of End : 27.02.2009

Length of the Tunnel : 250m

Diameter of the Tunnel : 4.60m x4.20m

Fethiye Eşen-l HES


Main Company : Göltaş A.Ş- Alke İnşaat A.Ş

Date of Start : 10.08.2009

Date of End : 31.10.2010

Length of the Tunnel : 2329m

Diameter of the Tunnel : 3.80m x4.80m

Adana Toros HES


Main Company : Bereket Enerji

Date of Start : 18.03.2010

Date of End : 22.04.2011

Length of the Tunnel : 10582m

Diameter of the Tunnel : 4.60m x4.60m

Ankara Pozantı Highway Çiftehan-Pozantı Junction


Main Company : Tekfen-Turbin-Özdemir AO

Date of Start : 05.08.2010

Date of End : 03.09.2010

Length of the Tunnel : 4300m2

Diameter of the Tunnel : Püskürtme Beton

Göktaş-II HES


Main Company : Bereket Enerji A.Ş

Date of Start : 03.01.2011

Date of End : 27.12.2011

Length of the Tunnel : 6000m

Diameter of the Tunnel : 8.10m x8.10m

Göktaş I-II HPP–Derivation Tunnel


Main Company : Bereket Enerji A.Ş

Date of Start : 17.07.2011

Date of End : 23.08.2011

Length of the Tunnel : 400m

Diameter of the Tunnel : 8.10m x8.10m

Gümüşhane Köprübaşı HES


Main Company : ARSAN ARITMA VE İNŞAAT A.Ş.

Date of Start : 12.09.2011

Date of End : 16.01.2012

Length of the Tunnel : 1624m

Diameter of the Tunnel : 4.20m x4.00m

Akseki Çenger HES


Main Company : Kanyon Enerji

Date of Start : 24.11.2011

Date of End : 16.12.2011

Length of the Tunnel : 200m

Diameter of the Tunnel : 4.20m x4.40m

Göktaş-I Supply Tunnel


Main Company : Bereket Enerji A.Ş

Date of Start : 02.03.2012

Date of End : 05.12.2012

Length of the Tunnel : 1170m

Diameter of the Tunnel : 8,10m x8,10m

Düzce Aksu HPP Energy Tunnel


Main Company : Bereket Enerji A.Ş

Date of Start : 09.12.2012

Date of End : 07.02.2013

Length of the Tunnel : 205m

Diameter of the Tunnel : 3,60m x4,00m

Blue Regulator and Apa Hotamış Supply Channel


Main Company : Özaltın-Cengiz-İlci-Ortaklığı

Date of Start : 06.08.2012

Date of End : 24.12.2013

Length of the Tunnel : 3.743m

Diameter of the Tunnel : 8.50m x8.50m